Objectives / Activities / Deliverable

General objective:

  • Development of the cross-border public transportation using electric buses.

Specific objective:

Specific objective 1: Development of the electric buses.

Specific objective 2: Improving of the range for the electric buses using renewable energy.

 

G.A. No. 1. Project management.

Activity 1.1. Organizing the teams project and implementation of the project.

Deliverable:

No Deliverable
1 Appointment decision for the team of the project TUIASI
2 Appointment decision for the team of the project UTM
3 5 Individual work contracts with its 5 annexes at the individual work contract TUIASI
4 6 Individual work contracts with its 6 annexes at the individual work contract UTM
5 Minute regarding the first work meeting at TUIASI
6 Minute regarding the first work meeting at UTM
7 Working plans (1 TUIASI; 1 UTM)

 

Activity 1.2. Monitoring, evaluation, technical report and financial report into the project

Deliverable:

No Deliverable
1 Monitoring time sheets, TUIASI
2 Monitoring time sheets, UTM
3 Progress report no. 1
4 Progress report no. 2
5 Intermediate internal report
6 Final Report
7 Audit – UTM
8

Practical guideline

Activity 1.3. Equipments acquisition and promotional materials

Deliverable:

No

Deliverable

1

List of the acquired equipment, TUIASI

2

List of the acquired equipment, UTM

3

List of the promotional materials – visibility, TUIASI

4

List of the promotional materials – visibility, UTM