Objectives / Activities / Deliverable
General objective:
- Development of the cross-border public transportation using electric buses.
Specific objective:
Specific objective 1: Development of the electric buses.
Specific objective 2: Improving of the range for the electric buses using renewable energy.
G.A. No. 1. Project management.
Activity 1.1. Organizing the teams project and implementation of the project.
Deliverable:
| No | Deliverable |
| 1 | Appointment decision for the team of the project TUIASI |
| 2 | Appointment decision for the team of the project UTM |
| 3 | 5 Individual work contracts with its 5 annexes at the individual work contract TUIASI |
| 4 | 6 Individual work contracts with its 6 annexes at the individual work contract UTM |
| 5 | Minute regarding the first work meeting at TUIASI |
| 6 | Minute regarding the first work meeting at UTM |
| 7 | Working plans (1 TUIASI; 1 UTM) |
Activity 1.2. Monitoring, evaluation, technical report and financial report into the project
Deliverable:
| No | Deliverable |
| 1 | Monitoring time sheets, TUIASI |
| 2 | Monitoring time sheets, UTM |
| 3 | Progress report no. 1 |
| 4 | Progress report no. 2 |
| 5 | Intermediate internal report |
| 6 | Final Report |
| 7 | Audit – UTM |
| 8 |
Practical guideline |
Activity 1.3. Equipments acquisition and promotional materials
Deliverable:
|
No |
Deliverable |
|
1 |
List of the acquired equipment, TUIASI |
|
2 |
List of the acquired equipment, UTM |
|
3 |
List of the promotional materials – visibility, TUIASI |
|
4 |
List of the promotional materials – visibility, UTM |